Indicator | Details |
Transport medium | Raw water |
Engineering quantity | 1356 meters |
Original pipe specifications | DN1000 (Carbon steel pipe) |
Work pressure | 1.6MPa |
Construction period | 7 days (2023 production) |
Construction environment | High-level reservoir, high-altitude cold area, mountainous terrain |
1. High environmental adaptability requirements: The low-temperature conditions in frigid regions impose stringent demands on material weather resistance and construction techniques;
2. Difficult construction logistics: Mountainous terrain combined with high-altitude reservoir settings creates significant challenges for transporting primary materials and equipment;
3. Complex pipeline pretreatment: Aquatic organisms present within pipes necessitate pulse cleaning technology for removal;
4. Water pressure compatibility: Ensuring restored seal integrity under 1.6MPa high-pressure operating conditions.
1. Achieved the first application of flexible composite hose repair technology in reservoir scenarios;
2. Overcame challenges in repairing water supply pipelines in frigid regions, validating the technology's environmental adaptability;
3. Ensured the safety of raw water conveyance for elevated reservoirs, providing a reference for similar projects in the Northeast Plateau Plain.
Leveraging advanced restoration technology, we have successfully overcome the industry-wide challenge of repairing water supply pipelines in high-altitude reservoirs within frigid regions, ensuring stable delivery of raw water from critical water sources. As a trusted technical partner, we have provided invaluable experience for similar pipeline restoration projects in Northeast China's cold regions! — Reservoir Management Office